The local story

For decades, this triangle between Duke Street, Van Dorn Street and I-395 meant Landmark Mall. Now the question is what all those cranes, new streets and construction fences are actually building.

Landmark Center opened in 1965, became an enclosed mall in 1989 and largely closed in 2017. Demolition began in 2022. WestEnd Alexandria is the replacement: a 52-acre district where a hospital campus sits alongside homes, shops, gathering spaces and transit.

The important distinction is timing. The hospital, private town center and public transportation projects are separate work streams. This guide follows the official record available on October 4, 2026; announced dates remain targets, and renderings show plans rather than finished conditions.

01

The big picture

A new district, built one block at a time.

Alexandria approved the redevelopment framework in July 2021 for up to approximately four million square feet. That is a development envelope, not four million square feet already under construction. Foulger-Pratt leads the wider redevelopment; Inova’s medical campus is its anchor.

On the site plan, lettered blocks help explain the work. Aspect occupies E1 and G. The townhomes occupy L and M. The hospital is its own campus. Parks and new streets connect these pieces. “Town center” describes the broader mixed-use neighborhood, rather than a single shopping center opening on one day.

Developer master plan labeling the hospital campus, Aspect blocks E1 and G, townhome areas L and M and other WestEnd blocks
Master redevelopment plan from December 8, 2025. Use the letters to locate each project. Other labels, including hotel, medical office and housing types, describe the earlier overall program, not projects confirmed underway. Van Metre’s later announcement governs the 110-townhome description.WestEnd developer presentation / City of Alexandria ↗Enlarge / open full drawing ↗
02

Hospital construction

The structure is up. The hospital is not open yet.

Construction began in 2024. Clark’s April 16, 2026 update marked structural completion of the fourth and final campus building. Topping out means the structure has reached its final height; it does not mean patients can move in.

Clark reported the next work as glass curtain walls and precast exterior panels, alongside interior work already underway on lower floors. Mechanical, electrical and plumbing systems are a major part of this stage. A hospital needs much more than finished walls before it can operate.

Inova continues to list a 2028 opening, with a preliminary schedule subject to change. The most recent verified milestone used here is April’s topping out. The construction photographs below are dated individually; neither is an October site inspection.

Dated construction view of the Inova hospital frame, cranes and new streets at WestEnd on December 1, 2025
Actual construction on December 1, 2025, reproduced in the developer presentation. The hospital frame and new streets are visible. Historical progress photograph; not October 2026 conditions.WestEnd developer presentation / City of Alexandria ↗Enlarge / open full drawing ↗
Construction team at the April 2026 Inova Alexandria Hospital topping-out milestone with concrete structure behind them
Hospital topping-out milestone, photo published by Clark on April 16, 2026. The completed structural milestone is later than the December photograph above. This is a team photograph, not an overview of the whole campus.Clark Construction ↗Enlarge / open full drawing ↗
03

Inside the medical campus

Three places for care, with different jobs.

The Alexandria hospital is planned with 192 licensed inpatient beds in fully private rooms. Inova identifies cardiac and neurosciences care, women’s health, cancer care and outpatient specialty services. These are Alexandria figures; the separate Franconia-Springfield hospital is a different construction project.

Clark describes a 663,000-square-foot hospital, a roughly 107,700-square-foot cancer center and an approximately 84,800-square-foot specialty care center. The campus also needs a central utility plant and parking. The larger master-plan allowance and the measured area of these care buildings describe different scopes; they should not be added together.

The new campus replaces the current Inova Alexandria Hospital on Seminary Road. Inova says the old hospital parcels will be decommissioned after the new campus is completed in 2028. Until a move is officially announced, a construction milestone at Landmark should not be read as a change in where existing hospital care is delivered.

ComponentPlanned roleConstruction reference
Hospital192 licensed inpatient beds; private rooms and inpatient care663,000 sq. ft.
Cancer centerStandalone Inova Schar Cancer centerAbout 107,700 sq. ft.
Specialty care centerOutpatient specialty servicesAbout 84,800 sq. ft.
Hospital campus rendering showing the tower, lower clinical buildings, landscaped spaces and parking garages
Design rendering published on Clark’s hospital project page. It helps explain the separate buildings around the inpatient tower. A view of the planned completed campus, not a construction photograph.Via Clark Construction; design by Ballinger and Ennead ↗Enlarge / open full drawing ↗
04

The first town-center buildings

Aspect puts homes above the ground-floor activity.

Foulger-Pratt announced construction in March 2026 on Aspect, the first residential community at WestEnd. Its two seven-story buildings provide 390 apartments and approximately 66,000 square feet of ground-floor retail. A connecting sky bridge is planned for resident fitness and shared amenities.

The developer announced a 16,000-square-foot lease with Tierra Encantada, a Spanish-immersion early education provider. That is one identified tenant, rather than a complete list of stores and restaurants. A retail rendering does not establish which businesses will open or when.

The March announcement targets delivery in the first quarter of 2028. The December 2025 preconstruction deck had shown late 2027 and 60,000 square feet of retail; the later announcement is the reference here for Aspect’s schedule and retail area. Early diagrams remain useful for understanding the layout.

Street-level Aspect rendering with apartment buildings, ground-floor storefronts and a public plaza
Aspect rendering published by Clark / CFP in June 2026. Apartments face the planned plaza and commercial frontage. Generic cafe and shop signs illustrate the design; they are not a confirmed tenant list.Clark Construction / CFP ↗Enlarge / open full drawing ↗
05

The for-sale homes

110 townhomes have a builder, but no verified opening date.

Van Metre’s August 18, 2026 announcement says it acquired the townhome site in July. Blocks L and M are planned for 110 three-story homes with front and rear terraces and private garages. This moves the story beyond the earlier City approval.

The builder plans Early Access by mid-2027, with floor plans, prices and details to follow as design and permitting advance. Early Access is a sales milestone, not a move-in date. The acquisition announcement does not establish that all 110 homes are already under construction.

06

Parks and public life

The spaces between the buildings are part of the project.

The December 2025 presentation illustrates a Central Plaza with summer gathering space and a winter ice-rink configuration, plus Terrace Park, a paseo and a playground. A paseo is a pedestrian passage: here, a connection through the district rather than another road for cars.

The deck also sequences parks and pavilions with Aspect’s construction. Those images explain the intended public realm, not completed amenities or confirmed operating schedules. The playground design was explicitly conceptual and still being refined.

This is the part to watch at ground level. Can someone get from a bus stop to a shop or appointment on a continuous sidewalk? Is there a usable place to sit or play before every block is finished? Those are practical questions for a neighborhood that will open in phases.

Summer Central Plaza plan showing retail pavilions, a lawn, tree grove and seating
Central Plaza summer configuration, December 2025 developer plan. A lawn, shaded seating and retail pavilions organize the gathering spaces. Proposed design; not an open park.WestEnd developer presentation / City of Alexandria ↗Enlarge / open full drawing ↗
Winter Central Plaza plan showing an ice rink in the urban plaza
Winter configuration of the same plaza, December 2025. The ice rink shows intended seasonal use, not a confirmed opening or operating calendar.WestEnd developer presentation / City of Alexandria ↗Enlarge / open full drawing ↗
Terrace Park plan along Van Dorn Street showing a boardwalk, lawn, courts, dog area and pedestrian passage
Terrace Park and paseo plan from December 2025. Labels show an elevated boardwalk, recreation courts, lawn and dog exercise area beside Van Dorn Street. These are planned amenities, not verified completed facilities.WestEnd developer presentation / City of Alexandria ↗Enlarge / open full drawing ↗
07

Streets, buses and access

Some of the construction sits outside the new buildings.

The West Alexandria Transit Center is planned as a six-bay bus facility serving DASH, Metrobus and future West End and Duke Street bus rapid transit connections. The City reports 30% design plans complete and permanent construction not started, with construction anticipated in 2027. Temporary bus operations continue separately. This is a bus hub; it is not a new Metrorail station.

The City’s I-395 ramp project modifies the northbound I-395 exit to eastbound Duke Street for access to the new hospital, including direct emergency-vehicle access. The City lists this project as active construction, with an overall construction-phase window through August 2028. Its June update warned of intermittent closures for survey work; that notice does not establish today’s lane closures.

A separate pedestrian-access project covers North Van Dorn Street between roughly Duke Street and Holmes Run Parkway. Its published construction schedule is March 2027–August 2029, with design continuing into early 2027. In other words, the hospital’s 2028 target does not mean every surrounding pedestrian improvement will be finished at the same time.

For a trip through the area, check the City’s project notices and WestEnd’s updates before leaving. The developer page still carries a March–May 2026 nighttime Duke Street notice; its dates should not be reused as an October closure announcement.

City map with a red dotted pedestrian-access project area along North Van Dorn Street by WestEnd
City locator map for the separate pedestrian-access project. The red dotted line marks the approximate work area along North Van Dorn Street. The map is not a current closure diagram or a completed-works plan.City of Alexandria ↗Enlarge / open full drawing ↗
08

What happens next

A timeline to read without treating targets as guarantees.

The clearest way to follow WestEnd is by project, rather than by a single completion countdown. Hospital opening, apartment delivery, townhome sales and street improvements each have their own dependencies.

For nearby homeowners and buyers, more healthcare, homes and local activity could change the area’s everyday convenience. The records do not establish a guaranteed increase in home values. Compare actual access, construction impacts and delivered amenities with the renderings when deciding how this location fits your needs.

ProjectVerified progressNext announced milestone
Inova campusStructure topped out in April 20262028 opening target; preliminary
Aspect apartments + retailConstruction announced March 2026First quarter 2028 delivery target
Van Metre townhomesSite acquired July 2026; 110 homes plannedEarly Access planned by mid-2027; move-in date unverified
Parks + pavilionsShown in developer construction sequencingPhased with development; opening dates unverified
Permanent bus transit centerSeparate from temporary bus operationsConstruction anticipated in 2027; 30% design plans complete
Pedestrian access improvementsDesign and coordination underwayMarch 2027–August 2029 construction schedule

Trent’s original videos

Watch the reports behind this story.

Why this matters locally

Landmark’s replacement is a new piece of Alexandria: healthcare, homes and daily destinations connected by streets and public spaces. What matters is how those pieces work together as they arrive.

Sources and further reading

Where the reporting comes from.

This article draws on public records, official statements, and attributed local reporting. Each link opens the original source.

  1. City of Alexandria: Landmark/Van Dorn approvals and submissions ↗
  2. Inova: Alexandria campus and preliminary 2028 schedule ↗
  3. Clark Construction: April 16, 2026 topping-out and next construction stages ↗
  4. Inova Newsroom: April 2026 hospital capacity and services ↗
  5. Foulger-Pratt: March 2026 Aspect construction announcement ↗
  6. Developer preconstruction presentation: Aspect, parks and pavilions, December 8, 2025 ↗
  7. Van Metre Companies: August 18, 2026 townhome acquisition announcement ↗
  8. City of Alexandria: West Alexandria Transit Center ↗
  9. City of Alexandria: I-395 ramp improvements ↗
  10. City of Alexandria: pedestrian access improvements at Landmark ↗
  11. Inova: future of the existing Seminary Road campus ↗
  12. WestEnd Alexandria: construction notices ↗
  13. City of Alexandria: Landmark history fact sheet ↗
  14. Clark / CFP: June 11, 2026 Aspect construction update ↗